$50B price tag to fix
aging rail transit in Chicago, 6 other cities
April 30, 2009
(AP) - More than one-third of the trains, equipment and facilities of the
nation's seven largest rail transit agencies are near the end of their useful
life or past that point, the government said Thursday. Many have components
that are defective or may be critically damaged.
A report by the Federal Transit Administration estimates it will cost $50 billion
to bring the rail systems in Chicago, Boston, New York, New Jersey, San
Francisco, Philadelphia and Washington, D.C., into good repair and $5.9 billion
a year to maintain them.
Those seven systems carry 80 percent of the nation's rail transit passengers,
or more than 3 billion passenger trips a year. They also include some of the
oldest subways and commuter railroads. Some of their facilities date back more
than a century.
"In a period of rising congestion and fuel prices, these services and the
infrastructure and rolling stock that support them, are critical to the
transportation needs and quality of life of the communities they serve,"
the report said.
"At the same time, this infrastructure is aging and the level of
reinvestment appears insufficient to address a growing backlog of deferred
investment needs," the report said.
Sen. Richard Durbin, D-Ill., one of 11 senators who requested the report, said
older transit systems have received a declining share of federal rail transit
aid as newer systems have come online. In 1993, the seven largest rail transit
systems received 90 percent of federal modernization funds, compared with 70
percent today.
The study rated 8 percent of the assets of the seven rail transit agencies as
in poor condition because they have outlived their useful life and are in need
of immediate repair and replacement and may have critically damaged parts. An
additional 27 percent were rated in marginal condition because they are near or
past their useful life and may have defective or deteriorated components,
requiring increasing maintenance.
Excluding the seven large system, less than 20 percent of the assets of rail
transit systems nationally are in poor or marginal condition, the study said.
The study comes as Congress is gearing up to overhaul highway and transit
programs over the next six years through soon-to-be-introduced legislation that
some lawmakers estimated will seek about a half trillion dollars.